Construction Litigation:Pease Air National Guard Base, New Hampshire On behalf of our client, Reed & Reed, Inc, we have brought a lawsuit in the federal district court in Maine against the general contractor, Cairns & Sons, Inc, for the contractor's failure to follow transfer specifications in connection with paving work that Reed & Reed performed. The lawsuit focuses on the General Contractor's breach of contractual requirements for delivering concrete to the slipform paver used by Reed & Reed and the contractor's failure to provide adequate quality testing to identify deviations from project specifications in a timely manner. |
|
|